|
CONCRETE
FORMS TO CONCRETE FOOTINGS
concrete
defects
concrete
sacking
concretefloor.html
concrete
stairs
about
concrete tools
Forming
concrete
walls with strip ease system rent this system
-components:
flat
metal ties, steel bar walers, slotted plywood forms, hinged corners
-nail out
side
plate 19mm outside bldg line to concrete footing
-erect all
corners
plumb and nail to bottom plate
-attach top
plate
between corners
-attach
plywood
forms to bottom and top plate nail lightly
-insert flat
metal
ties into slots
-pull steel
waler
bars through slots
-build window
and
door bucks
-set up
inside
plywood forms threading onto ties
-brace and
straighten outside wall
-set pour
strip
- pour
walls
-strip walers
by
using hammer on steel bars


FAST FOOT
A material footing,,, works great available at concrete forming outlets
pouring
CONCRETE FORMING WITH DOUBLE WALERS


NOTE: plate
must be
3/4" off of building line to allow for forming plywood





nail
off all strong backs, corner locks
with 3.25" duplex nails


the
4"x6" brace is used to hold
form work against existing wall
preventing
movement


the
corner strong back is picked up by one
waler and the blocking and wedge are picked up by the other set
of walers
batter
boards

-
are placed around excavations so that string
lines can be put up on the grid lines
the
battered boards should be erected using a
3,4,5 triangle from the bottom of the excavation example 4 feet of
depth you would place batter board three feet from edge.
-try
to keep the horizontals close so the
strings touch when they cross
battered
walls

have
one side sloped the other side vertically
plumb often used as retaining walls the sloped sides OFTEN NOT ALWAYS
towards the retained ground.. steel
is stronger on battered side
beam
band slabs
-ensure
that scaffolding is at right elevation
-joists
centred at right spacing
-ensure
beams are built in centre of scaffolding
beam
pockets

-bulkhead
off beam pockets in top of walls make
sure pour heights are at right elevation to ease stripping and
eliminate chipping and skirting

beam
sides
-plumb
-
brace every three to four feet
-top
2x4 on edge
-bottom
plate well nailed
-ensure
packers for slab are not cantilevered
braces
-form
adjusters(FA)s or turnbuckles
-braces
must be angled less than 45°
-ideal
brace is 2/3 of the way up wall
-ledgers
are horizontal braces usually under
slab soffits
-spreaders
brace between sheathing to keep
exact separation for wall thickness
-adjustable
pipe braces for larger pours
-ribbon
bracing of columns
bucks:
windows, doors and other openings


-
cut plywood 1 or 2 mm smaller than wall
thickness
-plywood
form chase the ends
-
frame buck with two by four back cut ends
slightly to ease stripping
-
use nailing blocks on one side of concrete
form to hang pre made buck at the proper elevation
-
cross braces on bucks that are deep in the
wall
-
place a
wood keyway nailing strip on outside of bucks when using wooden frames
in concrete wall
bulkheads
-ends
of walls


the
dry tie prevents the bulkhead from
moving
-changes
of elevations
-cut
2 mm
smaller than actual wall size
capitals
top
of columns used to support flat slabs
chamfer
-
used to finish corners and for strike off on
top of walls
circular
-use
rebar as walers and 38 by 140 studs
climbing
slip
climbing
cold
joint
-where
two pours meet
-on
walls use a key way and rebar through the
bulkhead
-below
grade use a waterstop
construction
joints as above
-
bulkheads
key-wayed and holed for rebar
-footings
keywayed or roughened
-rustification
strips to blend pours
Corbels

-
are thickening of walls at top
How
to build:
Shoring
method:



-regular
forms ,
-one
wall full height,
-corbel
wall shorter,
-then
place a back wall behind shorter wall
ends at same height
-
double top plate for a beam on the top of
corbel supporting walls
-
then cross joist between the walls with angle
cut for corbel on one end of joist
-attach
2x4 plate to angle cut
-place
studs for back of corbel up from joists,
these studs are cut to proper angle for bottom of corbel, then soffit
with plywood
Bracing
method:
-expand
wall at the corbel by using plywood
gussets nailed to bottom stud wall and it’s offset stud wall
-cut
top of gusset to the proper angle for
corbel
-
the bottom stud should be cut at the correct
angle to also support soffit
-cover
gussets with the plywood soffit
corners
How
to:

-out
side corners can be pre built to the
thickness of the wall then plywood panels will match up inside wall
to outside wall
-
waling of outside corners
first a corner lock against the
wales
than nail the walers together then
place kickers on the outside tongues
-this
is called lacing the corner
dams
mass
concrete lifts
domes
are
concrete shelled roofs include: domes,
hyperbolic paraboloids, barrel and folded plate roofs -beams around the
domes are pre-stressed with post tensioning cables .. .shells can be as
thin as 50 mm
door
bucks for cast in place metal
door frames

-when
placing metal frames fur out frame so
that it is same as wall thickness
-plug
any holes with rubber plugs
-ensure
that metal frame is kicked securely on
all sides
-place
frame tightly against concrete form
-kickers
on closing panel must fit snug against
metal frame
elevator
door bucks

-
cut plywood for buck 1 or 2 mm smaller than
wall thickness.. .then frame with 2x4
-
the top plywood of the buck
forms a cap the 2x4 frame runs
right
across the top and is supported by the side frames of the buck
-
cross braces on bucks width and height
embeds
and templates
-be
very careful precision is needed .. .use
string lines , check diagonals and centre to centre distances mistakes
here can cause lots of back charges! on templates mark out the centre
lines of the template and work from the centre out to the holes
embeds
are
placed in concrete to:
-protect
edges
-weld
plates
-for
brick of facing ledgers
-
to weld beams
or columns
-anchor
bolt
for wall plates 12 bolt every 2400 inserted to a depth of at least 100
-
as reglets for waterproofing (do not oil
caulking will not adhere)
-
often the use of a plywood template
is needed
-smooth
dowels are often greased to be used
between
slabs that might have lateral movement
-dowels
can be placed wet, drilled and epoxied
or screwed into cast in place inserts
engineer’s
schedule
-form
work construction
-placement
of concrete
-order
of stripping
-type
of shoring
-location
of shoring
-duration
of curing
-curing
conditions
-duration
of reshoring
-reshoring
placement
flat
plate slabs
flat
slab with columns
flat
slabs
flat
slabs with columns, dropped plates and
capitals
floors
fly
tables
-
aluma stringers, joists, braces, legs,,
backing rod, infill panels, rollers and cable jacks
-carefully
locate pick points for balance
Moving:
-screw
jack legs down until bottom chord rests
on rollers (floor jacks maybe needed)
-keep
skirting and filler panels attached to
table for ease of installation
-tie
off table before rolling forward to attach
slings
-move
forms outwards with cable jack
-remove
pickup covers connect to crane run
crane out connect power winch to second set of pick up points
-guide
form out and lift
-reshore
at engineered points
-
mark leg points hold table with crane fold
down legs and set on marks
-adjust
legs with jacks
-place
infills
footings
minimums:
twice as wide as wall and the same
thickness as the wall width
-use
stepped footings on sloped ground 600 long
600 deep vertical connection at least 150, 400 for very deep slopes
-
every side can run wild when using chased
sides for the footings

-concrete
foundations 150 to 300 thick
-crushed
stone or coarse granular mat is used
around perimeter and under basement slab for better drainage and radon
mitigation
-new
polystyrene forms are developed for
basement forming and insulation and vapour proofing
-wood
joists and beams set in concrete walls
less than 150above grade must have 12 air space and sit on a moisture
barrier or be treated with a decay preservative
-after
stripping all tie holes must be filled
and waterproofed
-anchour
bolts for sill plates 12.7 spaced at
1853 NBC embedded 100
gangs
-braced
securely
-tapered
ties or coil rods example shows double
waler wall
-giant
gang bottoms anchored with bolts drilled
into footing
gangs,
walls

PLES
-place,
length, elevation, size
PLESS
-plumb.
level, even, square, straight
check
list:
-braced
special notice to meeting of walls “T”
-studs
and wales are in place
-insert
seams are tight
-no
nails protrude through skin
-all
ties and wedges secure
-corners
laced and kicked
-bulkhead
correctly placed and nailed
-embeds
are placed accurately and secured
-bucks
are placed braced and nailed
-leveling
strip right elevation and secure
-stripped
with out wastage of material
hoarding
are
used over
streets to protect public
-2.5
meters high
-roof
slopes towards site
-
must have warning lights if on street
isolation
joints
give
and take materials must be compressionable
joints
-isolation
joints .. give and take
-slab
use give and take strips or saw cuts
-walls
use chamfer
-rebar
usually every second horizontal
-control
joints grooved and less rebar ..
“T” strips forced into a groove
top
pulled off leaving plastic insert concrete is trowelled finished over
top
-wall
control joints combined thickness of wood
inserts should be 1/5 of wall thickness, insert strips should be 20
beveled to 12 .. control joints are necessary in walls greater than 25
m, first at natural weaknesses doors, windows then 3 m from corners and
then 6 m apart
-cold
joints: should be cleaned, roughened,
wetted, a layer of bonding material
or a layer 12 of grout before new concrete is poured on top
-construction
joints below grade use water
stop, keyways and bulkheads are designed to take rebar
joists
for false work
6.5
inch
alumas or 4x6 douglas fir, they sit
on stringers to support soffits on suspended falsework
-deflection
of 19 plywood Forms:
24
inch centres support 100 lb. per square foot
20
inch centres support 200 lb.
16
inch centres support 400 lb.
12
inch centres support 800 lb.
8
inch centres support 1600 lb.
4
inch centres support 3200 lb.
Pressure
of concrete at rate ft/hour vibrated
averages
from 150 to 220 psf depending on
temperature
ties,
braces, double wales
Pressure of
concrete at:
100lbs
tie every 6 feet
200lbs
tie every 5 feet
400lbs
tie every 4 feet
800lbs
tie every 3 feet
1200lbs
tie every 2 feet
3600lbs
tie every 1 foot
keyways
made
from 2 by material should be beveled and
oiled or greased with lithium
kickers
-used
to lock corners on walls nailed to the
outlooks of the walers (on the wall sides of the outlook)
ledgers
-ledges
to hold joists or soffits
offsets
-a
narrowing of the wall usually to carry a
slab or masonry veneer finish
-easiest
way is to fur out the form wall
pilaster
a
column
placed in the wall

How
to:

-
ply wood sides are cut to fit between the
wall and outside of pilaster
-
stiffeners for sides run from wall waler to
pilaster walers
build
so they tighten with the pressure of
concrete


reglets,
reveals
-
reglets are inserts in concrete to hold
flashing
-reveals
are inserts attached to concrete Forms
for decorative edges
-rustification
strips used at top of walls to
blend pours from one floor to next

Round
and
curved walls use 10 m rebar as walers,
cut plates to
proper radius out of 3/4" plywood,
nail strong
backs
to plates to give wall desired shape,
tight radius
use
hardboard as forming sheathing nail to stromg backs
RETAINING
WALLS

Retaining
wall
thickness , footing size and reinforcement all increase with height of
wall.
sauna
tube
-round
fibre tube for pouring columns
-must
be kept dry
build
38 by 89 crib to hold on floor and use
“FA” to brace the top
-lower pump
hose
down tube to pour
- sauna rebar
reinforcment called a zone, combines verts and ties
scaffold
-holds
falsework for floor soffits
sheathing
-high
density plywood for
smooth finish has an opaque resin
finish
-form
ply
usually three quarter inch and 7 ply (layers)
-oiled
200 uses?
slip
forming
-
inward tilt called battered is about .3%
outward from bottom
-yokes
hold Forms together with walers attached
yokes are comparable to outer strong backs
-300
mm per
hour by jack assemblies embedded in concrete base
-finishers
scaffold below form attached to yoke
walers
-lifting
load depends on jack and jack rods
-jack
rods must be sleeved for reuse
-slip
form wales are 38 lumber
slip
Forms are usually about 1200 deep
snap
ties
-
flat from sheet metal: strap ties,
and strip ease ties
-coils
used with , coil cones, coil rod, plates
and bolts
-standard
cone ties 6000 lb. come in long end
and short end use wedges or brackets are coned to
act as spacers
spandrels
-
outer face of slab is the spandrel beam
concrete
stairs
stairs
-
under side is soffit
stringers
7.5
inch alumas sit on top of scaffold heads
for suspended slabs hold 6.5 joists
studs
-
2 by 4 strong backs against plywood
-rule
of thumb for centers of 2 by 4 studs on
3/4 inch plywood with out deflection
-24
inch centres 100 lb.
-20
inch centres 200 lb.
-16
inch centres 400 lb.
-12
inch centre 800 lb.
-8
inch centre 1600 lb.
-4
inch centres 3200 lb.

1... 4x6 joists are laid on top of packers are not nailed or fastened
2... shown are aluma beam packers they sit on top of plywood beam
bottom soffit they are not fastened
3...beam side form plywood note: in structural drawing the depth of
beam includes thickness of slab
4...these are the top plate of the beam side they are placed on edge
for strength and nailed every 12" through beam side plywood... if your
4x6 are tight to beam side no other bracing is required if not brace
back to deck or use ties and walers...Important note when pouring
concrete all beams and girders are poured first and then the slab
5... the plywood beam soffit sits on aluma joists and is nailed off
with one nail in each corner of plywood sheet
6... 2x4 plate nailed off to plywood soffit and into wood fillers on
aluma joists, bottom of beam side is nailed to this .. also note that
this joint beam bottom and soffit should have a piece of chamfer if
beam is going to be exposed below
7... the aluma joists laid out on top of aluma stringers... the end
aluma joists are often bolted to stringers
8... aluma stringers are clipped onto heads of scaffold... when
building set aluma stringers in heads and bolt on to end points
immediately set elevations of intermediate heads and use 2 clips per
head
9...heads must support full stringer ...for example end frame
would be moved over so stringer covers complete top of head
10... frames are set and spaced to engineers specification
for weight loads
11... feet are adjusted to proper elevations...when setting elevations
it is the combined thickness of all parts: 3/4" ply,aluma joists, aluma
stringer, heads, frames and feet
straighten concrete wall forms


T WALL HAVE
IMMENSE
PRESSURE SO INCREASE REINFORCEMENTS TO SAVE ON DEFLECTION

tilt
ups
-
wood Forms
-steel
trowel slab
-slab
must be beefed up for extra loading re
crane
-release
agents
-cure
about 1 week before tilt
-strong
back help to stiffen panel when tilting
-lots
of rebar is required
-embeds
or pick up inserts..
wall and knee brace inserts..
strong back inserts.. .
-
aligned after set up with adjustable braces
-inserts
must be engineered to distribute load
strain
-pilaster
clamps secure concrete form work
between tilt up panels
-to
tilt up panel cranes are best positioned to
either side
-tilt
panel is lifted as close to vertical as
possible to reduce strain on concrete
-set
in place between steel dowels at bottom
-panel
must be plumbed with all knee braces
installed and bolted to floor before crane release
-minimum
of 2 braces per panel
-permanent
secured by welding to floor plates
walls
double
walers..double end
ties at
1',3',5',7' horizontally and vertically on an eight foot wall
-strong
backs or studs are used behind form ply
for strength,, concrete 150lbs/cubic foot
example 6'
wall
force on bottom of wall 6x150=900lbs
-rule
of thumb re force of concrete and stud
spacing to prevent deflection of plywood
-24
inches stud centres 100 lb.
20
inch stud centres 200 lb.
16
inch stud centres 400 lb.
12
inch stud centres 800 lb.
8
inch stud centres 1600 lb.
4
inch stud centres 3200 lb.
|