
Framing
steel beam
joists
attached to wood ledger bolted to bottom
flange
joists
cut back and scabbed across the top
with
12 mm space
for shrinkage under scab

-joists
butting into a steel beam must sit on a
wood ledger and have a scab across the top joining the two joists the
scab must have a 12 air
space to allow for joist shrinkage


-or
wood ledger bolted to beam and joists nailed
to ledger with full bearing on top of beam
-steel
beams W or S .. w indicates wide flange...the first number is the
dimension of the depth and the
next number is the weight in kilograms per metre
-steel
beams I or wide flange if using wood
plate wood plate on bottom flange it must be bolted on 6.3mm
diameter bolts at 600 centres


built
up beams are nailed together with 89 (3.5") nails...two rows at 400
(16") centres each laminated piece... the butts have to land with in 6
" of quarter points unless they fall on a support
framing
start from one corner of
building and ensure
all framing starts from this designated corner,
-the ideal
concept is joist, stud, joist,
rafter all bear in a straight line down to foundation
Floor
framing members... detailed views
boxing joist AKA:
box,
header, rim, comb or
combing joist
or frame
floor to ledger
bearing
wall or beam carrying floor joists...birds eye view
framing
a
flush beam... view elevation
minimum bearing 89 (3.5")
HEADER TO CARRY FLOOR LOAD
framing
stairwell opening...birds eye view

I
joist truss
floor
system IJ's are a great system for long spans..great for large rooms
without bearing walls...
the
IJ shown does not show the rim joist ... I glue the bottom of the joist
to the mud sill an use two nails one of each side of the bottom chord
I
use a plywood stiffener one on each side of the web at each end of IJ
.. through nails and clamp off nails the stiffener has about
half
an inch gap at top
I
use squash blocks both sides of IJ they are about a sixteenth of an
inch taller than IJ at all load bearing walls
When
you add rim board (not shown) through nail ...one nail into each top
and bottom chord
Rim
board is toe nailed into plate one nail every 300
When
using joist hangers keep the IJ back from the flush beam at least 1/8
of inch and a dab of glue between hanger and bottom chord

When
sheathing nail and glue plywood..IJ are designed to have a solid
ceiling like Gyp rock applied if no gyp rock strap bottoms with1x4 at 6
ft centres
Nail
plywood 5/8" t and g 150 on edge and 300 in field ...use deformed
nails...and 1/4" continuous bead of glue
Note
squash blocks and IJ blocking when carrying a shear wall or load
bearing wall above
a non load
bearing wall
above just need stiffeners..although I like to use both a stiffener and
a squash block


If
you are cantilevering the IJ system use a 5/8" sheet plywood
reinforcement BOTH SIDES nailed with 62 (2.5") nails every 150 (six
inches) into
the bottom and top chord ...MAX CANTILEVER 2 FEET/ 600MM
EXTENDS BACK INTO BUILDING MINIMUM 4' /1200MM
sub-floor
-use
a panel floor overlay minimum 6 mm
when you have a lumber
sub floor or a panel sub floor with unsupported edges.. . use:
hardboard, plywood, wafer board, particle board nails 22.. staples 28
-joints
should be offset by 200 from sub-floor
-edge nailed at 150
field
at 200
Construction
types
of
beams:
Paralams
are strands of lumber glued and pressured together... as below

Timberstrand
is like many layers of oriented strand board laminated together... as
above
Laminated
veneer lumber aka LVL are like many layers of plywood laminated together
-solid
timber
-glue
laminated
-veneer
laminated 45 thick..
lightweight..
free from shrinkage.. and
defect free.. longer
spans
-strand
laminated long wood strands bonded and
cured under pressure microwave energy
-built-up
crown side up bolted together or
nailed double row of 89’s at 450Cf..
.quarter point closest to column can have join
at quarter point
(150 variable) see diagram
above
-89
minimum beam bearing
-38 minimum joist
bearing
-steel
beams I or wide flange if using wood
plate wood plate on bottom flange it must be bolted on 6.3mm
diameter bolts at 600 centres
Calculating
beam size: number of floors,
supported joist length 1/2 each side..
spacing of columns..
use beam tables
-wood
beams in concrete need a 12 mm air space
unless treated lumber is used
-steel
beams W or S .. w indicates wide flange...the first number is the
dimension of the depth and the
next number is the weight in kilograms per metre
-pony
wall may carry joists.. laid out at 400
first is 380.. bottom
plate pre drilled for anchor bolts, pony wall does not give any lateral
strength
-layout
should always start from one corner for
the whole building.. joists.. plywood
floor.. stud walls.. rafters..
wall sheathing.. roof
sheathing
-wood columns
minimum 140 x
140 when built up
76’s nails at 300, columns usually spaced 2.4 to 3 meters
Construction
bridging




-
cross bridging 38x38 or strapping with 19x89 at 2100 centres
- strongest is both cross bridging and strapping under cross bridging
with 19 by 89
-cross
bridging pieces should not touch each
other..will squeak, cross bridging should be cut short so they do not
extend
past joist depth
-the bottoms of
cross
bridging pieces are not nailed off until house is completed
-strapping..nails
two 57’s per joist
-blocking
is done alternate sides of a chalk
line
-metal
bridging done after sheathing
-bridging
and blocking should be tight and
secure
cross bridging is
not
required where a panel
ceiling is applied to bottom of floor
Construction
columns
-minimum
wood 140x140 (186 diameter) must be as
wide as the beam they support or have a steel 7
mm plate saddle to support the beam
-steel
columns must be 73 diameter, wall
thickness of 5 mm
and a steel cap at each end (telepost)
-concrete
columns must be 200 square or 230
diameter with metal saddle
-damp
proofing must be used between wood and
concrete post if post is more than 150 below grade
-post saddles,
bottom
embedded in concrete
Joists
types:
-lumber
-manufactured
plywood web joist called I joists or I trusses aka
IJs
-steel
truss
Numbers:
Floor
joists nailed to plate with three 82’s

over
lapped at beam nailed each end with two
76’s
-header
joists must have five 82’s or three
101’s at trimmer joists and tail joists
-double
headers and double trimmers must have
two staggered rows of 76’s at 300 centres
-or
metal hangers
-floor
joists must have a bearing of 38
-over
lap joist must not overlap beam by more
than 300
-joists
butting into a steel beam must sit on a
wood ledger and have a scab across the top joining the two joists the
scab must have a 12 air
space to allow for joist shrinkage
-
boxing joists should be of the same size as
joists and ends should land on an end of a joist
-layout
joists positions on the boxing joist
from the longest straightest wall.. offset overlapping joists.. .make
sure that first joist space is 20 smaller so that the plywood will fit
the spaces on center.. .always offset towards the starting point so
that the sheathing fits.. .lay out on the boxing joists openings for
stairwells, chimneys, partition, plumbing fixtures
-
non bearing wall supported by blocking
between two joists 38x89 at 1.2CENTRES
-load bearing wall
must be
supported in the
direction of the beam it must be within 600 of the beam if it is
supporting a floor above or
900 from the beam if it is not supporting a floor ...IJ floors must
have bearing walls directly on top of support below
-check
bathroom layouts to ensure the joists
are not blocking soil pipes if blocked install headers and tail joists
.. headers should
be doubled if they exceed 1200. trimmer joists doubled when the length
of header joist exceeds 800, if head joist exceeds 3200 it must be
calculated for size, if header joist exceed 2000 the trimmer joists
must be calculated for size
stairs
stairwell
opening..
first trimmers to first headers with five 82’s.. first headers to tail
joists with five 82’s (I
USE HANGERS..) first headers
and second headers with 82’s, first
trimmers to second headers five 82’s..
nail second trimmers to first trimmers
with 82’s spaced at 300 CENTRES
-first
headers..
tail joists.. second headers..
second trimmers.. second
joist
-joist
hangers or ledgers used with flush beam
-joists
embedded in concrete foundation wall
must have 2/3rds of their depth buried, ends should be treated with
preservatives
Construction
numbers
sheathing
(
if you use lumber lay at 45°
degrees to joists)
-tongue
and groove 5/8" plywood (should use)
-grain
across joists.. lay ply wood 90 degrees to joists
-
glue and use ring nails driven well below surface ..
screwing and gluing popular screws must have same shear strength as
nails
-offset seams
start...second row with half sheet
-T&G
snap a line.. . bead of glue.. .
stay back 50 from snap line with glue.. . place T&G on edge by
glue. place grooved edge by chalkline.. . drop to land in position..
.line up.. .tack corners.. .nail to code 150 on edges 300 in field..
.leave grooved side nails loose so next sheet can be eased in.. do
whole row.. start second row with partial sheet.. .push in by hand try
not to smear glue bead.. .sledge hammer and long
block to fit tightly
-edge
nail 150 field 300
-minimum
thickness of sub floor with 400
centred joists is 15.5.. 600 centres 18.5
square edge (non
T&G) must be blocked
38 x 38 or have an overlay panel type floor of 6
Construction
subfloors
-plywood
oriented strand board, wafer board,
shiplap, t and g lumber
-lumber
no wider than 184 and 19 thick use 51’s
two per joist
square
edge panel blocked with 38 x 38
-panels
nailed 150 edge 300 field, ringed nails
-use of elastomeric
glue
improves floor
Construction
of
access floors
offices,
computer and electrical running under
floor for ease of assembly and ease of access
-floors
are steel frames with removable panels
covered withh resilient flooring or carpets
-floors
are adjustable for height
-the floor depth
space is
150 to 300
|