WALL FRAMING
to CLADDING

OUT BOUND LINK http://www.kithomebasics.com/index.html
Also
see exterior wall
moisture barrier and rain screen

A
few basics..
the
string line and a chalk line are musts for laying out straight walls,
the string line is more accurate than a chalk line... the chalk line
will pick up bows and imperfections and transfer them into the snapped
line ...
NOTE:
On a windy day your string line will be bowed sometimes considerably...
tape measures are more accurate than
levels
plumbing
a stud with a level as you build will give
a decent wall but the level will pick up any bows or twists in the stud
and the wall will not be perfect
when
placing studs always pull your numbers from same end of wall and layout
accurate marks on your plates...
Start
at one corner layout all your sixteen inch centres for the whole wall
come
back to the same corner and layout all your wall openings in the same
wall
the
studs under windows become jack studs...
Layout
your door and window trimmers(aka Jack studs) to carry the lintels (aka
Headers)
Now
layout the plates on your work deck... I like to tack the bottom plate
to the floor to hold it in place while building and squaring walls
Place your full size
studs bows or crowns down and nail off three wire gun nails per stud
from top of plate
Diagonals
are always equal in any rectangle,,, when building your walls always
ensure all measurements are equal re plate lengths and stud heights,
wall openings... then when wall is built check your diagonals to make
sure your walls are square .. again your tape measure is more
accurate than any building square or even sheets of plywood


Note
when building your lintel/header the blocking for sheathing goes under
the header, but the trimmer goes straight to the header... this is
because of shrinkage, once wall is built, sheath it with your plywood,
keep1/8" space between sheets for expansion



NOTES:
go to Wall moisture
barrier
Four
ways
to connect
exterior wall to interior wall
Interior
wall meets exterior wall can be joined
four ways re drywall backing:
#1-horizontal
blocking across stud bay top,
bottom and middle
#2-a
2x6 flat IN EXTERIOR WALL attached to 2x4 INTERIOR stud,

#3-
multiple 2x4 s on flat in exterior
stud bay spread to accept one from interior, interior top plate over
laps

# 4 exterior drywalled right
through
and
interior fitted to, interior top plate over laps`
Numbers
framing
-nailing
through plates into stud end
...
two 82’s nails or toenail studs... using four 63’s nails at
each end
-double
studs forming a post... require 76’s
nails at 750 on centre
-
doubled top wall plates 76’s nails at 600 on centre
-sole
plates nailed to joists through sub floor
82’s nails at 400on centre

-PETS...
precision end trimmed studs
-the standard for
lintels
are
doubled up 38x 235 with a 38 stacked
underneath
the 38 is not supported by the cripples,
the 235 often sandwich plywood as a furring piece/ jacks are not used
above the lintel
-lintels
are nailed together with two rows of
82’s at 450 on centre
-lintels
are attached to studs with two 82’s at
each end
-when
the lintel span is too great for 235 a
286 is used and the top plate is omitted and a 19 is stacked under the
286 this maintains the same depth as a 235
-jack
studs are used under the roughed in sill
of windows
minimum
size stud for exterior wall with or
with out attic space and supporting a roof is 38x64
-184
lumber for exterior sheathing is nailed
with 51’s two per support wider lumber use three/support note diagonal
bracing is required
-solid sheathing edge nail
at 150 field at 300
-sheathing
can butt subfloor or over lap and be
nailed to the box joist
-
when building wall on floor pull diaganols
from corner to corner to insure framing is square before you nail
sheathing
-nail
upright kickers on box joist
before tilt up of the wall.. this blocks it in place for nailing
-studs
at 600 minimum plywood size is 7.5 ... good practice use 12.5
-fiber
or gyprock must use a nail head of 11
-backing
is used when ever a fixture is
attached to a wall with out a stud for the fastener
-when
prefabbing interior partitions do the
longest first
-as
a fire block studs are doubled around
interior openings
-staggered
stud construction the end stud is
the same thickness as the plate
sound
transmission and duplex homes party wall construction

“STC”
sound transmission class
-the
higher the “STC number the more resistance
to sound
-heat
loss designs also reduce noise
transmission
best: 50
STC .. double walls with air space 12 sound deadening board and 12 gyprock both sides
best ceiling: 45 STC
floor: carpet, underlay, 5/8 floor, 1/2 inch floor,
ceiling: 1/2 gypsum wall board
stand -off
wall
-vertical
wall truss system
-stand
off wall system house built and then a
truss system,(hanging from roof trusses and nailed to horizontal
blocking,) is used to build a non bearing insulated wall on the out side
note the polyethylene vapor barrier goes on the inside of the plywood sheathing of the outside
interior wall
-vapor
barrier is applied over sheathing of
exterior load bearing wall
-the
width of poly
between top plates at least 600
-window frames lined
with plywood
vapor
air
and
moisture
barrier
-when
furring out studs on walls the
polyethylene .15 vapor barrier goes between
the stud and the strapping
-vapor
barriers are installed on the warm side
of the wall.. condensation
takes place at the dew point temperature
-air
barriers are used to prevent the passage
of air.. . they are lapped a minimum of 100 mm and taped.. can be any
where in wall system
-moisture
barrier sheathing paper must be edge
nailed every 150 mm
-water is prevented
by a moisture barrier usually a 30 minute building paper with doubled
coverage
exterior
wall
protection
from thermal contact heat loss:
-wall
plates, studs use wider studs at larger
centers 89 to 140 increases RSI from 2.1 to 3.5; eliminate some corner
studs and studs at wall intersection and use drywall clips
-furred
out interior wall with horizontal
furring leaves space for electrical with out damaging vapor barrier
-double
stud wall construction use an
interior or exterior
load bearing wall/ interior load bearing from outside in: siding,
weather barrier, framing with batt insulation, cavity filled with
insulation, plywood sheathing, polyethylene ..15, framing with batt
insulation gyprock (note must have special trust design to support roof
exterior wall is supported on plywood connector and diagonal bracing to
foundation make poly contiguous with out breaks, exterior bearing
double wall construction is similar to standard practices from outside in: siding, weather barrier,
sheathing, load bearing wall with batt insulation cavity with batt
insulation, polyethylene ..15, framed
wall with batt insulation
-stand
off wall system house built and a truss
system, hanging from roof trusses and nailed to horizontal blocking, is
used to build a non bearing insulated wall on the outside note the
polyethylene vapor barrier goes on the inside of the sheathing
note
in all double wall constructions the
polyethylene ..15 is placed on the outside of the studs of the inner
wall before the batt insulation is installed
-no
to single pane windows
-no to aluminum
window frames
protection
from thermal contact heat loss:
-wall
plates, studs use wider studs at larger
centers 89 to 140 increases RSI from 2.1 to 3.5; eliminate some corner
studs and studs at wall intersection and use drywall clips
-furred
out interior wall with horizontal
furring leaves space for electrical with out damaging vapor barrier
-double
stud wall construction use an
interior or exterior
load bearing wall/ interior load bearing from outside in: siding,
weather barrier, framing with batt insulation, cavity filled with
insulation, plywood sheathing, polyethylene ..15, framing with batt
insulation gyprock (note must have special trust design to support roof
exterior wall is supported on plywood connector and diagonal bracing to
foundation make poly contiguous with out breaks, exterior bearing
double wall construction is similar to standard practices from outside in: siding, weather barrier,
sheathing, load bearing wall with batt insulation cavity with batt
insulation, polyethylene ..15, framed
wall with batt insulation
-stand
off wall system house built and a truss
system, hanging from roof trusses and nailed to horizontal blocking, is
used to build a non bearing insulated wall on the outside note the
polyethylene vapor barrier goes on the inside of the sheathing
note
in all double wall constructions the
polyethylene ..15 is placed on the outside of the studs of the inner
wall before the batt insulation is installed
-no
to single pane windows
-no to aluminum
window frames
heat

heat
transfer: conduction .. by material /
convection
.. by air
/ radiation .by waves
-solar
energy gains... face larger windows to
the south
-when
efficiently sealed a fresh air exchanger
will be needed... to conserve energy use an air to air heat exchanger
-air
must be exchanged at the rate of .5 per
hour during heating season
-kitchens
require an air exchange of 50 liters
per second
-polystyrene
foam insulation cannot be attached
with adhesives containing solvents or hydro carbons
-expanded
polystyrene foam insulation is known
as bead board
-thermal
breaks prevent heat lost due to
conduction
-rigid
fiberglass insulation and extruded
polystyrene foam can be used instead of plywood sheathing .. .must use
a head diameter of 19 mm
-header
insulation bags must be perforated on
inside face
-degree
days = total number of days times the
number of degrees below 18C
-sound transmission
by waves .. materials have class ratings for their ability to reduce
noises
moisture barrier
-moisture
leaks below grade: concrete walls
coated with two coats of asphalt emulsion,
-underside
concrete floors should have
polyethylene vapor
barrier (up walls 150)
-under
slab can be insulated with polystyrene
before slab is placed
-concrete
basement wall
polyethylene on wall must not go to 1 foot from top
then a studded wall insulated , ..15
polyethylene and then gyprock
-joist line
insulation between joists from exterior wall to interior wall
size and shape
-building
size smaller more energy efficient
-layout
of rooms with out using unnecessary
halls
-extra
large utility rooms
-poorly
designed entrances
-poorly
designed stairwell openings
-lot orientation re windows, trees, rooms
and prevailing winds and sun shine
vapor barriers, insulation
-permeation
of water vapor is called the” Perm”
value = nanogram/pascal second/meter squared, perm value of
15 is good
-note
in all double wall constructions the
polyethylene ..15 is placed on the outside of the studs of the inner
wall before the batt insulation is installed all joints of polyethylene
are overlapped 100 and caulked, stapled to door and window frames and
taped to any wires and pipes
-ideally
it is best not to locate any
electrical boxes in outside wall
-
at double plate where wall meets roof truss
the polyethylene 400 strip is
fed between the plates so that it can be sealed to the ceiling
polyethylene
-plywood
window boxes are installed in truss
walls through the structural wall as a continuous unit, plywood liner
sealed to vapor barrier and to flashing and to window frame drywall
over plywood with a plastic
“j” bead against window frame
- nonexpandable foam
insulation between rough
frame and window frame press polyethylene vapor barrier into foam
before it hardens to complete seal
-air
pan for electric boxes
-air passage must be
kept open from soffit through to attic
fire stops
-3
meter height for blocking
-fire
stops for dropped ceiling
-fire
stop 12.7 gypsum wallboard behind stair
stringers and landings
-Douglas
fir plywood fire rated at 150
-lumber must be 38
for fire stop
blocking
-fire
breaks
-blocking
behind hand rails
-behind
skirting on stairs
-washroom mirrors,
grab bars, TP dispensers, sinks, tubs
drywall
finishing
-
fasteners cover with joint compound
-
prefill joints greater than 12
-prefilled
v grooved eased edge
-fill
recess.. . center tape.. .embed tape in
center.. . smooth out air bubbles
-
joints compound tape compound start with 150
blade after drying
layer with 250 blade feather edges
-wet
sponge after set up
-
outside corner use a corner bead
-compounds:
tape compound, topping compound,
all purpose, setting type
tapes:
paper or fiberglass
Corner beads:
expanded metal or metal with paper
numbers
installation
-nail
heads 1/4 inch dimpled
-
nails penetrate
20 into wood 18 ring nail
-screws:
w, s, s 12, g, .. .s and s12 are self
tapping.. w has deeper thread
-adhesives:
stud or laminate adhesives or
contact
-nail
ceiling at 175
-nail
walls at 200
-
nails at 12 from edge
-double
nail at 50 apart ...spaced 175 at edge 300 in field
-screws
300 on ceiling 400 on walls
-adhesives
6 single bead double bead at joints
fasteners at 400 on outside perimeter and 400 on outside perimeter of
ceilings and 600 in field of ceiling
Order
of assembly: drywall ceilings.. . top of wall.. .
bottom of wall, with steel stud direction of layout is into the
channel, cutouts chalk box push to mark and cut out or use a cut out
tool
Tricks: floating
ceiling nailed 175 from edge, floating corners 175 not nailed, curves
wet board, blocking 25 above tubs.. . 7 gap below board to tub, showers do not apply
directly over a vapor barrier, cement board use a ceramic adhesive on
edges, cement board holding ceramics screw 100 on center, multi layer
of GB offset by 250
SHEAR WALLS

Shear
walls are designed to resist lateral forces such as wind.. or siesmic
activity.. they correspond with the opener concepts of interior design
and the large openings for windows and doors... so often seen in
today's house designs.. shear walls work together with floor diaphrams
(floor systems) to stabalize the structure
sizes
6 remodeling, curved
surfaces
8
manufactured houses
10
repair remodeling
12
to .15 single application residential
19 to 25 core board
liner board
drywall types



-regular,
eased edged,
-type
X...fireguard 5/8"
-water
resistant, green board
-(fire
stop) backing board backing board is the
first layer of any two layer system,
-coreboard
fits into special design metal studs
used for fire resistant applications (elevators, stairs),
-predecorated,
-liner
board,
-blue
board , -exterior yellow,
-cement
or concrete board, showers, behind tiling
-12.5 controlled
density is stronger designed for ceiling applications
with 600 centers
steel studs
-studs,
runners and channels
studs:
-25
gauge non
load bearing partition
-20
gauge non load bearing curtain wall
-16
gauge for load bearing partitions
-punch
outs to allow for stiffeners and for
electrical wiring
1
5/8, 2 1/2, 3 5/8, 4 and 6 with legs of 1 and
1 1/4
-stock
lengths of 8, 9, 10, 12, 16, and custom
lengths up to 28
-runners
or tracks:
-top
and bottom horizontal members
-
steel track also called runner toed in for a
friction grip to studs
-track
or runner attachment to floor :
2
inches from each end and at 24 inches on
centre at corners butt channels or overlap
at
intersections butt or lapped
-concrete
powder actuated, adhesive
-tile
and stone , adhesive or predrilled holes
and expansion anchors
-track
or runner to ceiling: into furring,
-exposed grid ceiling
screw track to suspension system
-concrete
ceiling same fasteners as floor
-to
install studs cut them about 1/4 inch short
-install
first studs at corners and partition
intersections, at corners place the stud about 50 away from
intersecting wall to allow for room to use drill
-run
dry wall pass intersecting walls were
possible
-insert
studs into runner and twist into place
screw or crimp bottom... plumb and clamp top then screw top.. lay out
the stud spacing from this top stud
-place
all studs in position with the channels
pointing in the same direction web punchouts aligned
-fasten
all studs except the sides at door
jambs
-a
one piece door frame may be applied before
gyprock or a knock down three
piece may be applied after gyprocking
-
doors and windows frame three piece by
starting a rough opening with two vertical studs, -cut headers from
short length of track or runner, make about 300 longer than opening
snip and bend each end to run down the stud, install jack studs over
the opening
-single piece door frame
place in rough opening
plumb and attach
bottom
to floor then sides to studs and studs to top
and bottom runners for large doors the steel studs should be made from
a heavier gauge 20
steel channel furring:
are
formed from 16 guage 7/8 by 2 9/16
-lengths
of 10, 16, 20 feet channels are used
in walls and suspended ceilings
-when
used for lateral bracing of walls they
are slipped through the stud punchout and welded or clipped to steel
stud
-girt
are wall stiffeners that go between studs
they are applied the same as the header
-girt
are used behind drywall joints or for
electrical chases
-pass
through holes, every 24 inches, must line
up in studs to allow for the services
-double
wall and chases for many services a
double wall is built the
studs must face the same direction and be lined up together for
attachment purposes
if
the space is under 300 the second wall may
have smaller stud sizes and be reinforced with dry wall across the 300
space
-if
a partition does not go to the ceiling it
must be stiffened at 3000 intervals with studs to ceiling, reinforce
the partition with a wood stiffener across the top
-use
toggle bolts through steel frame to fasten
objects for heavy objects wood blocking is required
-splicing
of steel studs lapped for 200 maximum
extension is 300
-chase
wall formed by screwing the backs of two
studs together to get a thicker wall
-staggered
wall is made by using a larger
channel and crimping studs to alternate sides
-furring
channel:
-drywall
furring
are hat shaped pieces with a knurled
face made from 20 or 25 gauge steel size 7/8 by 2 9/16 available in
lengths of 12 feet
they
are attached to walls and ceilings at 24
inch centres on opposite sides of furring channel, used
for screw attachment of gypsum panels
and plaster bases furring pieces may be lapped and tied together
-wall
furring is preferred vertically at 24
inch centres, when placed horizontally start from 4 inches off floor
and ceiling
-resilient
bar is similar to furring only one
side is attached to studs reduces the transmission of noise
-ceiling furring tie
wire, screwed to studs bolted to flanges, metal deck hangers
suspended
ceilings are formed with a carrying
channel and steel studs channel is supported from wire hangers at 1200
on centre
-furring
and track around pipes
-wall
furring
-furred
columns
-dropped
ceilings or bulkheads use cross
furring members
-resilient
furring to walls and ceiling and 150
from the corners, use 12.7 gypsum
backing 75 deep along floor and first resilient furring piece 600 up
from floor and spaced at 600
-seal
partition walls with two beads of
acoustic caulk to improve “STC”
tools:
aviation shears, guillotine,, hacksaw ,
straight edge, circle cutter wall board ripper
-saws,
rasps, crimpers, corner bead clinch ons
-lifters
and electric screw drivers
-cutoff
saw
-gypsum
board edges: beveled, chamfer, tongue
and groove, square edge and bull nose
-gypsum board comes
in standard or fire resistant which has glass fiber that holds board
together

METRIC
CONVERSION 25 = (APPROXIMATE) 1 "
|