-footings; concrete or pressure treated wood,
concrete on undisturbed soil must have drain pipes at 1200 on centre 60
diameter
-floor: concrete slab separated from wall with
a screed board, or wood sleepers, or suspended wood floor
-plywood 12.5 must be caulked to stud and to
each other sheet of plywood with a 2 to 3 gap
-holes and cuts must be treated with a non
leachable preservative
-stainless steel nails and staples
-hot dipped galvanized anchours and straps
- sealant must be compatible with PWF and
polyethylene .15
-drainage layer 10% fines # 4 sieve and the
rest up to 40
-whole excavation to 300 outside the wall
covered with 125 granular drainage layer
-sump pump 750 below basement floor surrounded up to 150 with granular
fill, pump or positive gravity drain, location easy access
|