|
|
|
|
|
Basement
floors CLICK
HERE FOR HOW TO PAGE
basement
floors

BLUEPRINT-TO-CONCRETE
slabs 25mpa exterior 30 mpa
- min. 75 thick
-slope to drain
-complete installation of sewer and other
subsurface work before pouring
-base of 100 crushed rock
(vapour and soil gas)
protection
- a layer of polyethylene .15 lapped 100 or “S”
roll roofing
-bond breaker between slab and walls and
columns (double layer tar paper)
-air entrained should use magnesium floats
-once water sheen has disappeared trowel and
edge - don’t over work causes dusting
-proper control jointing 4.5 to 6 meters in
either direction, and at columns and changes of widths of slab,
-control joint cuts should be 1/4 the thickness
of the slab
-cure for five to seven days ponding, wet
sacking etc. if using a curing membrane ensure that it is compatible
with any floor finishes
-slabs on grades should be 200 above finish
grades
-water repellent rigid insulation around
perimeter
- slab reinforced with 10m rebar at 600 centres
both ways
|
|
blueprint-to-concrete
STAIRS
CLICK
FOR HOW TO PAGE BLUEPRINT-TO-CONCRETE
STAIRS
blueprint-to-concrete
FOOTINGS
CLICK
HERE FOR HOW TO PAGE BLUEPRINT-TO-CONCRETE
FOOTINGS
|
| Defects concrete-defects
Repairing
concrete:
CLICK FOR HOW TO concrete sacking
blueprint-to-concrete FORMS CONCRETE-FORMS
|
|
Stamp
finish
blueprint-to-concrete stamping ...bull float fresh
concrete until flat and
smooth ..run the fresno over to remove any bug holes...
start
stamping when concrete is still relatively soft ... push your finger in
you should feel resistance your finger should stop at about 1/2"
... now sprinkle a liberal coating of release form
....now take the rubber stamp (you will need at least two)
..start in one corner place mat squarly to sides and if you weigh about
160 lbs

walk on it...make sure you given even pressure on all sides and middle
... now down next stamp tight and square to first stamp and
step off first stamp onto second and repeat...
lift up stamp from behind and place in front..
continue until done ... on a warm day you must work quickly...the
concrete does not wait or forgive you

|
|
blueprint-to-concrete
finish
slab
-screed to level
-float.. to
bring cream up and aggregate down - edge to round corners
- float, trowel, smooth hard finish, edge,
trowel
|
|
blueprint-to-concrete
finishing
bull
float
-angle bull float to handle is about 30°
-push down on handle for push stroke.. pull up on handle for pull
stroke
-the leading edge of bull float should be
raised slightly above concrete surface so it rides not ploughs the
concrete
-give the handle a shake as you go it causes
the concrete to settle
-work
concrete
until relatively smooth
-next large float is a “darby” a large hand
float
-once
concrete is relatively smooth you can run the fresno or a steel trowel
over the surface... wait for water to settle and trowel again.. do not
overwork wet concrete...but once surface water is gone don't be scared
to use the steel trowel as many times as you want
|
|
blueprint-to-concrete
finish
You
can use the
groover to cut your grooves specially for sidewalks and driveways
...for
slabs, you
can use a circular saw with a concrete blade... cut it as soon as you
can walk on it without scarring it..
set
the blade to
about 3/4 inch ad run the saw down a straight edge
|
|
blueprint-to-concrete
finish
floating,
edging
strike off, bull float, edger or/and groover,
float, wait until surface water is gone and trowel, edge, and groove..
progressively smaller trowels
(knee board and second float to support weight)
|
|
blueprint-to-concrete
finish
monolithic
pouring as a unit at one time often footings
and walls
|
|
blueprint-to-concrete
finish
screed
the guides that support the strike off bar
attached to stakes at the proper elevation
-screed board is also the give and take strip
between slab and wood foundation on “PWF”
|
|
blueprint-to-concrete
finish
striking
off
pull strike off board across screeds moving
back an forth for a smooth surface, bull float, trowel, strike bar, mag
float, edger, groover, power trowel
|
|
blueprint-to-concrete
finish
trowelling
after floating once surface water has
disappeared use a steel trowel
here
I am power
troweling.. push down onthe handle in the direction you want power
trowel to move...
Adjust
angle of
power trowel so the more you trowel the less steel touches the surface
Start
power
troweling when the concrete will hold your weight.. you may sink about
a quarter inch when you walk on it
When
you start
troweling full blade should touch concrete
Keep
troweling
until you have a very smooth surface
|
|
blueprint-to-concrete
finish walls
vibrating and placing
- small vibrator 15,000
- 5 to 15 seconds in concrete watch for bubble
to stop, shiny surface
- dip at about 1 and 1/2 radius of action
-150 into old layer
-thin forms external vibrators 1 to 2 minutes
- lifts from 1000 to 1200 deep
-stiff mix must be vibrated a large slump may
not need vibration
-over vibration causes segregation
- metal chutes 2:1
or 3:1 slopes
-squeeze pressure pump uses vacuum
- concrete can be pumped up to 150m
-conveyer use a down pipe
conveyers can cause
segregation
-a window in the form should be used if
concrete drops more than 1200 or a reducer hose lowered into wall
- slabs beams and girders are filled first then
slab
|
|
Finishing
waterproofing
-foundation walls - damp proofed with a layer
of asphalt from footing to finished grade
-poor soil drainage or water table high .. roofing felt applied over
asphalt emulsion .. lapped
like shingles two three layers over lapped 100 to 150 hot tar mopped on
between each layer
-back fill
once wall is supported or
concrete has
aged for 14 to 28 days
-where the back filled material is going to
carry a slab or sidewalk it must be compacted in 200 to 300 lifts
|
|
Floor
finishes
terrazzo marble chips embedded in top of a
concrete slab floor is ground and polished for a marble like finish
|
|
Floor
reshore
-reshores for at least three stories when
moving at one floor per week
-shores and reshores should be directly above
each other
-remove and reshore one at a time
-reshore under flat slabs centred between
columns
-decentring means removal of reshores
- engineered plans
|
|
Cutting
Plywood
radius
Use a radius stick nailed to plywood and
attached to saw plate
|
|
Cutting
Plywood rip guide for 12 to 24 inch cuts
Steel square, a two by slotted to accept one
side of square as a rip guide to run along side of plywood, make slider for other
tongue of square that fits rip guide off your circular saw
|
|
Layout
Layout square… with large wooden
square
Take: a steel square, two pieces of straight edge lumber, slot lumber
down middle with circular saw, steel square will tap in snug to these
slots : voila a large square
|
|
Layout
Layout arcs with wooden square
Make a Square wooden guide, and a stick , mark
the rise and then the run on the stick put a nail in either end of the
stick at these marks …… these nails will ride on the wood square…now
drill a hole and put a pencil through the stick where the rise and run
meet… lay stick on square push flat along one side… using nails as
guides push stick until flat on other side the scribed line is your arc
|
|
layout
Layout irregular shapes with tick stick
Tick stick … for irregular shaped filler pieces… you need sharpened tick
stick and plywood
scrap piece… put tick stick to corners,
lay out on plywood scrap,
use stick to
mark straight lines and slash marks for distance number each one, lay
plywood scrap on top of piece to be cut, use tick stick to layout
cutting points.. join points and cut
|
|
blueprint-to-concrete
Floor
suspended slab
- typical scaffold leg holds 10,000 lb.
-aluma stringers must be centred on heads must join at centre of head
-legs must be with in 12 of plumb in 3000
-form work must be wedged to building
-beams and girders must be filled first
-slopes must be filled from bottom to top
-safe working loads .. rule of thumb.. .of
aluma joist 1200 span 1200 kg or 2400 lb., 1800 span
600 kg or 1200 lb., 2400
span 225 kg or
450 LB per foot
-safe working load of stringers 1200 span 3000
lb. .. .1800 span 2000 lb.. .2400 span 1000 lb.
#1 post shore closed 9000 open 5000
#2 post shore closed 8000 open 5000
#3 post shore closed 7500 open 4500
#4 post shore closed 4500 open 2500
-Always wedge at slopes re heads and feet
|
|
blueprint-to-concrete
footings
columns
-single storey house column footings 640 x 640
x100
-two storey house 870 x 870 by 100
-pipes under footings should be backfilled with
concrete
-columns should be seperated from slab casting
with a bond breaker such as poly
-wood columns need to be treated and have a
moisture barrier between concrete and wood
- this footing uses a cloth membrane as the
form walls.. it worked great
|
|
|
Forms
water stop
-made from neoprene rubber
|
|
Forms
forms all about forming
wood shores
-single post
-“Ellis” double adjustable post
-“T” head single post
-double post with X braces
|
|
blueprint-to-concrete
Formulas
battered wall
average thickness of wall times length times
height
|
|
Formula
centerline
wall center line of a square, rectangle, L or T
shaped building (length plus width times two minus four wall thickness)
|
|
Formula
Radius from rise of chord
Radius = (rise squared plus run squared)
divided by 2 times the rise
Rise being the distance from chord to arc and
the run being 1/2 the chord
|
|
Formula
Chord for radius wall
Laying out an arc from a chord
Note:
-distance from chord to diameter is constant
and the run of your similar triangle
-the radius is your rake
-your rise are equal segments marked out on
your diameter
-the difference between your rake and run is
the rise of the chord for that given point
- make a diagram draw in your right triangles,
diameter, and chord formula becomes apparent
|
|
Formula
circle
-area of a circle pi*r squared
-area of circle is .786 of its square
-tangents forming a square about a circle are
the same length as the circle’s diameter
-chords forming a square in a circle are 1.4142
times the radius
-diagonal of a square is 1.4142 times one side
-cone 1/3 height times base area
|
|
Formula
girders and beams
subtract slab thickness from the beam sizes
when ordering concrete ..
. and when building beams
|
|
Formula
octagon
side of an octagon is found by dividing the
side of a square by 2.414 .. the
radius or 1/2 a
squares diagonal set on the squares corner points and arced across the
sides mark out an octagon. a circle’s 360 °
divided by the number of corners of a polygon give the angles of the
polygon .. . 90-180/# of polygon sides = the other angle of the polygon
|
|
Formula
volume cone, pyramid and frustum of
v = H/6(ab +(4am)+at)
|
|
Joints
expansion joints
use give and take strips between slab on grade
and walls and columns
-used any where there is old concrete meeting
new concrete that are subject to different movements
|
|
Placement
curing
- moisture and heat
-temperature ideal 10 to 15C
-excessive evaporation causes shrinkage and
cracking
-do not stain green concrete when curing with
sacks
-sprinkling
when not constant can
cause dry out and
crazing
and
cracking
-two coat curing should be applied at 90 degrees
-3 days 50% 7 days 70%
|
|
blueprint-to-concrete
Precast
order of assembly
-assembly sequence of pre cast buildings must
be given constant attention once materials are ready the crane should
be in constant use
-precast often welded in place also grouted and
bolt
-backing rod between pieces
-t joists roof or floor coated with concrete
topping
-two stage joint
-cables used for temporary support
|
|
blueprint-to-concrete
Rebar
columns
- form adjusting braces two ways
- steel banding
- avoid twisting the columns by alternating the
tension on form adjusters turn buckles
rebar for columns called zones
|
|
Rebar
coverage
-beams and columns rebar not exposed to
weather, minimum cover 40 for 35M exposed 50
-minimum cover for stirups ties and spirals 30
exposed 40
-structural slabs walls and joists not exposed
20 over 20M exposed 30
-structural shells 15M not exposed cover 15
exposed coverage 30
-footings cast on earth 75
for larger diameter bars 1.5
times bars diameter but no
more than 60
maximum aggregate size must be no greater than
1.4 times the rebar seperation
|
|
Rebar
curtains
re bar for walls are called wall curtains
-temperature bars are extra rebar.. . for walls
of different heights being poured monolithically ..
drying concrete shrinks ..
. the two
walls will shrink at different rates .. the extra rebar prevents
cracking
|
|
Rebar
post tensioning
is done after cast in place concrete is poured.. tendons are placed in
concrete .. when
concrete has cured the cables are tightened compressing the slab and
giving it extra strength against tensile loading
. the tendons are steel
cables encased
in metal or plastic sleeves anchour points are ductile iron and cables
are held by split wedges and cones..
concrete usually rises as
post
tensioning is applied .. . cables in hollow tubes are grouted into place
|
|
Rebar
pre- stressing
prestressing concrete puts the concrete into
compression which strengthens it for tensile stresses..
1/3 the steel is required
|
|
Rebar
pre- tensioning
is done in factory concrete before it is
shipped to job site, use steel cables called tendons
with the tension applied
before concrete
is poured.. after
concrete has set the end fasteners are released transferring the forces
internally pre stressed concrete is said to be in a pre compression
state
- only 1/3 of the steel needed
|
|
Rebar
sizes
size is indicative of the diameter before
roughening
|
|
Rebar
types
#40 -40000 lb.
#60 -60000 lb.
-steel rebar has the same thermal expansion as
concrete
-dowels are usually inserted 24 times their
diameter
|
|
Rebar
verticals
-dowels are usually inserted 24 times their
diameter
|
|
Repair
mortar
-use a patching mortar
- clean surface
-wet surface
- surface repairs: mortar
mixed to paste a slump of
50
-brushed on
- trowelled off
-partially dried and sacked
-deep repairs: mortar mixed fairly dry and put
on in layers drying each layer completely
-sides of patch area chiseled inwards
-some patches will need form work
-grouting and sack rubbing are done from top to
bottom
- no aggregate to be bigger than 1/2 the depth
of the repair
|
|
Slabs
false work
soffits and scaffolding used on suspended slabs
|
|
Slabs
flat plate slab
flat slab, columns
|
|
Slabs
flat slab
4 inches thick, dropped panel, column capital
|
|
Slabs
joist system
tapered end or fish tail,
floor slab minimum 2”,
girders,
rectangular or
round columns
|
|
Slabs
slab band
floor slab, slab bands, columns
|
|
Slabs
slab on grade
- sometimes grade beams
- dense base then 150 coarse gravel
- then polyethylene .15 under slab and up wall or poly under slab
and 25 sand cushion between slab and footing or premoulded joint filler
between slab and wall or a cast in place reglet at top of slab with a
sealed waterproof membrane
-usually rebar
-isolation joints every six meters isolated
from walls with fibre board
- 8 hours for slab sides to set
-
|
|
Slabs
two way ribbed
column with capital, dropped panel ribs or
joists, coffers or
deep recesses
|
|
blueprint-to-concrete
Strength
mixing temperature and curing
-ideal
10C° to 16 C°
-minimum 5C°
for three days
-must be maintained at 10°C
for 72 hours
-hot weather slabs should be kept moist for
seven days
-rapid surface evapouration due to hot weather
causes the slab to crack
-concrete mixing is effected by heat of
aggregate, easiest to cool is water, warm mixing water can cause a
flash set
- concrete should be placed within 11/2 hours
in hot weather, with heavy vehicle traffic
(expected delays) water is sometimes mixed into concrete enroute
- in hot weather Forms should be loosened ASAP,
in cold weather ALAP
- propane heaters in enclosed spaces cause
curing concrete to dust
|
|
Strength
aggregates
-round or cubic, clean and strong, fines less
than 5 -coarse 5 to 112 - make up 60 to 80 % of concrete, size of
aggregate should not be larger than 1/5th minimum dimension, or 1/3 the
slab or 3/4 of the clear space between rebar
|
|
Strength
air entrainment
-makes a stronger concrete more durable to
weathering
-7% air is a normal entrainment
|
|
Strength
coatings
curing spray
on membranes
|
|
Strength
concrete topping treatments
-curing compounds
.. . membranes chemicals ,
waxes,
protect from early drying
-sealers cure and seal from dusting
-protective treatments .. . from acids, salts,
oils, distillates, fats, beer ,milk, vinegar, etc.
-chemical hardeners .. .hard wearing surface
-metal or aggregate hardeners heavy wear surface
-bond breakers between layers re tilt up
-epoxies and adhesives create bonds between old
and new concrete
-pigments coloring
|
|
Strength
ingredients
- cement: calcium, aluminum oxide, ferrous
oxide, silica oxide .. . sets through hydration
Concrete numbers are all variables
-Concrete: 60 t0 80% aggregate , water to cement ratio 1:2 less
water makes a more impervious concrete, entrained air, plasticizers,
-good large aggregate should be clean, hard,
strong, cubical over 5 mm in size
-the water to cement ratio is based on kg
weights for every 1 kg of water you want 2 kg of cement
(-if it is based on volumes the ratio is one to
one one litre of water to one litre of cement)
-fine aggregate is based on the weight of
concrete for cubic metre and is 29%
-course aggregate based on the weight of
concrete for cubic meter is 52%
-fines should be under 5
mm
-slump is measured using a 100-200-300 slump
cone
-low slump is tied to stronger concrete 70 is
an example of low slump
-high slump 125 pump concrete should also have
10 to 15% more cement for pumping and aggregates should be round and
smooth
|
|
blueprint-to-concrete
strength
mpa
-compressive strength of concrete measured in
mega pascals
-25 to 30 mpa is very good concrete
-15 mpa minimum for walls, interior slabs on
ground (slumps 100), footings and house foundations slump must not
exceed 150
- 25 mpa minimum for garage floors sidewalks,
concrete stairs 5 to 8% air entrainment slump must not exceed
-garage floors150mm crushed rock or gravel and
75 concrete, foundation walls 150 thick and 150 above grade
|
|
Strength
other types
shotcrete for wall reinforcement applied by
pneumatic gun
- cementation with liquid grout used under
pressure to shore foundations, .. . making rock faces water tight .. .
under steel columns under machinery .. metallic aggregates sometimes
added to increase compression strength when the high water ratio has
weakened.. . with liquid grout water
proof forming is needed, air holes
to allow air to escape are
called grout
holes
- where a stronger grout is needed dry packing
can be used
-mortar is a mixture sand, water, cement used for bonding in
masonry construction and for patching and sacking concrete
-fiberglass reinforced concrete: tanks, pipes
boat hulls
-white cement blended for its white color for
stucco, decorative concrete
-blended hydraulic cement uses blast furnace
slag or pozzolan it sets slower at a lower heat than #10, the pozzolan
improves hardness of concrete
-waterproof concrete is made by adding a small
amount of stearate to clinker before grinding
-plastic cement used for making mortar, stucco,
it is #10 or #20 with a plasticizer
-expansive cement used to fill holes.. expands as it dries
|
|
Strength
paving
-slip Forms can layout large highways fast and
economically, skid resistant, air entrainment
protects from chemical
deicers and from
freeze thaw damage
-used for railroads, re: tunnels, bridges, ties
-soil cement a mixture of soil and cement Forms
a good hard surface for parking lots, roads and streets covered with a
layer of bituminous
|
|
Types 10
|
|
Types 20
|
|
Types 30
|
|
Types 40
|
|
Types 50
|
|
Types
additives or admixtures
-retardants slow down setting time .. hot weather
-plasticizers increase flow reduce need for
vibration
-superplasticizers more expensive than water
reducing agents .. produce a non vibrating
concrete .. also speed up setting times
-accelerators speed up setting time
-air entrainment increases strength and
protects from weathering
- cold weather
..
calcium chloride ..
an accelerator can damage
rebar should
never exceed 2% per volume
-work ability agents example air entrainment
increase the workability increase the slump
-damp proofing an initial water cement ratio of
less than 50% well cured will give a watertight finish .. and reduced water
permeability additives can be added
-bonding agents .. . epoxies
-grouting agents fill cracks and joints
-gas forming agents cause concrete to expand as
it cures
|
|
Types
aluminous
concrete made from high alumina cement reaches
28 day strength of portland cement in one day
-in 28 days its crushing strength is twice that
of portland concrete
|
|
Types
grout
is packed between the concrete base and the
shimmed up steel
column or machine plates
|
|
Types
hydraulic mortar
is used to patch leaking walls
|
|
Types
mortar
-used to stucco or patch concrete has no large
aggregates
|
|
Types
non vibrating
|
|
Types
plaino
self leveling gypsum -- a mixture that finds
its own level, is raked to spread evenly and dries to a smooth floor
finish ready for carpet or lino, .. . reduces sound and is a fire
separator between floors
|
|
Walls
damp proofing
-damp proofing is a layer of bituminous or a sheet of polyethylene
.15 seams lapped 100
-water proofing is proofing against hydrostatic
pressure a impermeable membrane (two layers of bitumen saturated felt
and covered with liquid bitumen
-floors subject to hydrostatic pressure must
have a wall membrane sealed to a floor membrane which is sandwiched
between two layers of 75 concrete

|