POURING YOUR
BASEMENT CONCRETEFLOOR

Basement
floors use 20mpa with
fibermesh added



-the
fiber mesh is an alternative method of basement concretefloor slab
reinforcement..
you can go
with 10m rebar at 600 centres both ways or no reinforcement at all
Concretefloor
Slabs are hard work, and
should have a crew of at least three.
I
suggest you use a concrete pump... a line pump is hard work but
delivers
the concrete at a slower pace which is a benefit... now if
you
are pumping the pump truck operator can be a huge help or a huge
handicap... you want the concrete delivered in manageable quantities...
a pump can piss out concrete so fast your head can spin... Be strict
and ask for his advice and help... you want a successful concretefloor
pour
First
decide on the elevation of your basement floor... remember if it is a
full basement that there are minimum height requirements... but your
best elevation is top of slab at 8 feet 3/4" below floor joists.. this
just makes framing out the basement so much easier( drywall and stud
sizes...when measuring remember your mud sill will sit on top of
foundation to carry your joists.. Now snap a chalk line at the proper
elevation all around basement wall..this is your top of CONCRETEFLOOR
OR top of pour
How much fill will you
need, minimum depth of concrete is three and a half inches you must
have a minimum
of six inches of...
a good substrate... a
load of 4mm and smaller sand is perfect for your needs
... now anything below
this can be filled with native backfill if granular or pit run gravel
This
substrate has to be level it does not hurt to snap a second line on
foundation wall 3 1/2inches below top of slab line... get out your
rakes
and level your substrate to this line... now the substrate
has to
be compacted hard... do not run a tamper over it once and say done....
do it again and again... now decide were your floor drain is going and
slope the sand towards it 1% grade is fine that translates to 1/2 in
four feet... if you take a four foot level and stick your finger under
the low end and it indicates level you are good to
go
Now-complete installation of sewer and
other subsurface work before pouring re sewer rough or any electrical
that needs to be below slab
I
know this messes up all your hard leveling work but this is the time to
do it... it ensures that your sewer lines do not sag... once this is
done re smooth your surface do no tamper over sewer lines.
Now it
should be looking good... layout a vapour barrier 6mil uv protected
poly...over lap any seams by 12 inches the weight of the concrete will
seal these seams...they do not have to be taped... but the poly should
run up the wall and be sealed to the wall with black acoustical seal...
this is only needed in areas where radon gas is a problem...
You can if you desire use-water
repellent rigid insulation around perimeter for insulation purposes the
top of the insulation must be even with top of sand substrate
Good
now... your slab prep is perfect it is a mirror image of your slab to
be.. find some nice straight 2x4s and lay them on edge out in parallel
lines about 7 feet apart these become your screed sticks when you pour
your concrete they give you the elevations of the floor
Your crew can pull the concrete with a 2x4 pull stick the third man
works behind the screeders he uses a rake and keeps the concrete being
pulled to a minimum and also ensures that there is always enough
concrete to pull (no voids)
I always put a foot wide whythe of concrete down the foundation wall
side and float it even with the pour line ... (the pour line can be
masked by wet concrete if you do not do this) this foot wide gives the
wall side elevation for the screeders to pull level from.. I also put
concrete on both sides of the 2x4 screed that lays on edge on ground..
this is just to keep it in position
Once you have an eight foot section done... grab your bull float and
run
it back and forth until surface is relatively smooth.... now continue
the next section over do not pull the 2x4 screed out of the concrete
until this section is poured and bull floated... now pull the screed
out ...this leaves an indent in the fresh concrete that you fill with a
few shovel fulls of concrete and then bull float again.
Continue until done.
Once finished, wait for surface water to disappear and when concrete
can hold your weight ... you sink when walking about 1/2inch...jump on
with your power trowel with floats on.. power trowel the surface until
uniformly smooth.. you will have cream floating in swirls this is
good..
hop off and wait for concrete to set some more... and then hop back
on... at some point pull the floats off and just use the steel trowels
keep doing this until you have a hard dense surface
You
will need to hand trowel the edges where the power trowel will not
reach ... spread your weight on a piece of sheathing or styrofoam
insulation to do this
Next morning using a circular saw with a concrete blade cut control
joints about 3/4" deep
-proper
control jointing 4.5 to 6 meters in either direction, and at columns
and changes of widths of slab,
-control
joint cuts should be 1/4 the thickness of the slab
-cure
for five to seven days ponding, wet sacking etc. if using a curing
membrane ensure that it is compatible with any floor finishes
-conretefloor
slabs
on grades should be 200 above finish grades
|